RapidRide R Line
即将来到 Seattle 南部
我们正在努力将 RapidRide 引入 Seattle 南部,以提供更好、更可靠的公交服务和便利设施!RapidRide R Line 将对目前的 Route 7 进行升级,并且为 downtown Seattle 和 Rainier Beach 之间的广大居民区提供服务,包括Chinatown-International District、Mount Baker、Columbia City、Hillman City、Brighton 以及 Dunlap。
King County Metro 和 Seattle Department of Transportation(SDOT,西雅图运输部)正在 Seattle 南部共同开展规划、外联以及参与工作。如需了解有关 Rainier Avenue S. 公交车车道项目施工的更多信息,请访问 SDOT 的网站。
Project overview
Metro is advancing the RapidRide R Line, building on Route 7’s long-standing role as a vital service for south Seattle communities.
- The R Line will operate entirely within the City of Seattle.
- It will provide service between downtown Seattle and the Rainier Beach Link light rail station, improving access to regional light rail service throughout the Puget Sound region.
- The line will run along S Jackson Street and Rainier Avenue S.
- It will connect communities from Downtown Seattle, Chinatown-International District (including Little Saigon), Mount Baker, Columbia City, Hillman City, Brighton, Dunlap, Rainier Valley and Rainier Beach.
Note about the Prentice Loop
RapidRide R Line is planned to end at the Rainier Beach Link station, and Metro is evaluating how transit service will continue to connect people traveling to and from areas south of S Henderson Street when the R Line begins service. As part of this work, Metro will engage the communities south of S Henderson Street to better understand their mobility needs and help inform future transit service decisions. The goal is to ensure transit service remains accessible, reliable, and easy to understand.
The RapidRide R Line project will improve transit travel time, reliability, and rider experience.
Recommended improvements include:
- Upgraded transit stations and shelters
- Enhanced lighting and passenger amenities
- Bus-only lanes
- Transit priority treatments
- Signal upgrades to reduce delays
- Safer pedestrian access to transit
- We know the community highly values Route 7 and uses it to access essential services, but we see areas for improvement. Buses frequently bunch together and are not reliable for getting to and from work, school, grocery stores, medical appointments, and more. RapidRide R Line will bring riders improvements to service quality, safety, and access.
- Metro brings RapidRide to communities with strong ridership, diverse riders and uses (e.g., local service and commuting), and connections to other transit modes.
- Many people use transit in south Seattle and as more people move to the region, we need to make it easier to get around. Route 7 is one of our busiest routes, serving over 11,000 people every day.
- Route 7 has always provided critical service for south Seattle residents. Metro wants to support better, more reliable service for Route 7 riders today and ensure it continues to meet the needs of this growing community.
Metro paused design work on RapidRide R Line in late 2020 due to COVID-19 related funding constraints. In November 2022, King County Council approved funding to continue developing RapidRide R Line. Since RapidRide R Line planning was paused in 2020, changes have occurred along and near the planned route, including new housing and commercial developments, street and sidewalk improvements, updated intersections, and other transportation projects led by City of Seattle, Sound Transit and the Washington State Department of Transportation. Metro reviewed these changes and revised the design to reflect current conditions to avoid duplication of work already completed.
The RapidRide R Line currently has a budget of $91.2 million. To help deliver the RapidRide R Line as soon as possible Metro will use county and potentially state funding to implement the project. We believe this funding approach will allow for a more predictability and will allow Metro to deliver the project benefits to the community faster.
The goals of the RapidRide R Line
- Increase access to reliable and frequent transit in the Rainier Valley.
- Improve the quality and ease of connecting to transit safely.
Attend an open house
Learn about the RapidRide R Line project, ask questions and share your feedback at an upcoming open house.
Project timeline
Project vision and early planning
RapidRide R Line was identified through Metro Connects, King County’s long-range plan for expanding frequent transit service, as a priority investment to improve transit along the Route 7 corridor. Serving one of Metro’s busiest and highest-ridership bus routes, the project is intended to improve speed, reliability, capacity, and the overall rider experience while providing better connections to jobs, schools, housing, and other destinations. This phase established the project vision and laid the groundwork for future corridor planning, funding and community engagement.
What happened in this phase
- Metro Connects identified RapidRide expansion as a long-term priority, and Route 7 as a priority for future RapidRide service.
- King County Council approved funding to begin planning and design for RapidRide R Line project.
- Metro developed an initial project concept in coordination with SDOT and other agency partners.
- The project was paused in 2020 due to COVID-19-related funding constraints and resumed in 2023 with updated planning work to reflect changes along the corridor.
- Metro advanced the project toward route adoption and the next phase of design.
Community engagement
What we did
From June to October 2019, Metro conducted community engagement during the RapidRide R Line needs assessment phase. Given the extensive community input on this line through previous work led by SDOT, we first needed to report back on what we had heard, explain how these issues and concerns will be reflected in design, and highlight future opportunities to influence decision-making. Metro had two main goals during the needs assessment phase: 1) re-engage Rainier Valley residents and introduce RapidRide R Line, and 2) gather community input on transportation needs and priorities to inform design concepts.
Engagement activities during phase 1 included interviews with community-based organizations (CBOs), service providers, and other community groups; in-person outreach consisted of tabling at community events and hosting community briefings in partnership with CBOs and other community partners; and an online survey was available in English, Simplified Chinese, Somali, Spanish, and Vietnamese. Across these channels, we gathered input on the following areas:
- Elements of the existing Route 7 that people appreciate most as well as areas for improvement
- Priority places people want to travel to and from when using Route 7
- Barriers to accessing transit and improvements to encourage more transit use
- Ways to effectively share information with, and gather input from, historically underrepresented or underserved communities
We also asked people to identify specific destinations along the Route 7 corridor that are important to serve and locations where they would like better access to transit or have safety concerns.
What we heard
Community input informed Metro’s design concepts and the communications and engagement activities planned for phase 2.
Early design
During the Planning Phase, Metro is refining the RapidRide R Line project concept to reflect current conditions along the corridor and the community’s evolving transportation needs. This work includes evaluating changes that have occurred since planning was paused, coordinating closely with partner agencies, and refining the proposed improvements to support faster, safer, and more reliable transit while aligning with other planned investments along the corridor.
What happened in this phase
- Metro evaluated corridor conditions and identified improvements to make transit faster, more reliable, and easier to use.
- The project concept is being refined through technical analysis and feedback from community members, riders, businesses, and partner agencies.
- Metro coordinated closely with SDOT to align the project with planned transportation improvements along the corridor.
- Metro is developing a preferred project concept that reflects current and future conditions along the corridor.
- Metro will seek King County Council approval of an Alignment Ordinance in early 2027 to confirm the route and station locations as the project advances into the next phase of design.
Community engagement
What we did
Phase 2: Metro gathered input on the preferred concept from November 2019 through March 2020. We had two community engagement goals:
- Share proposed RapidRide R Line station location options and gather feedback to inform the preferred concept, and
- Continue conducting intentional, inclusive, and equitable community engagement.
Metro’s engagement during phase 2 consisted of briefings, conversations, and walking tours with CBOs and other community groups; in-person outreach was performed through tabling at community events, gathering places, and housing communities; bus stop outreach; in-person open houses; an online open house available in English, simplified Chinese, Somali, Spanish, traditional Chinese, and Vietnamese; engaging with Route 7 operators; and briefings with city and county councilmembers.
We gathered feedback on the following elements of the RapidRide R Line preferred concept:
- Proposed station locations
- Projects to make it easier and safer to get to the bus
- Roadway and intersection upgrades to make the bus faster and more reliable.
The feedback we received helped refine Metro’s design for the preferred concept. Summary of this report is available in the Resources section below.
What we heard
Community input directly informed the current preferred concept through the following ways:
- Community feedback about service needs in Chinatown-International District influenced the decision to have RapidRide R Line serve both Maynard Avenue S and 8th Avenue S.
- Community feedback on station location options in Columbia City informed the decision to include RapidRide R Line station pairs at S Edmunds and S Dawson streets.
- We heard overwhelming community input and support about maintaining the existing S Walker Street station pair location and needed improvements to make it easier to safely access these stations.
- The connection to Link light rail at Rainier Beach Station brought through the S Henderson Street extension emerged as an important community priority.
Phase 3: In the third phase of engagement, Metro shared information about the final preferred concept which included station locations, proposed features, projects that enhance bus speed and reliability, and projects to make it easier and safer to get to the bus.
Now that Metro has restarted this work, the project will continue with its final phase of engagement by re-introducing and re-engaging community members. Outreach activities will consist of flyering across neighborhoods, engaging property owners, hosting virtual and in-person Open House, updating the website, and providing briefings upon request. The engagement phase will run from August 1 to 31, 2026.
Turning the project into a buildable plan
The Design Phase will further develop and refine the project recommendations from the preferred project concept.
What happens in this phase
- Station placement at the identified service intersections is further refined.
- Speed & Reliability treatments are further developed for implementation.
- Access to Transit Concepts are designed to provide enhanced access for cyclists and pedestrians.
- Project designs are evaluated for utility conflicts, property impacts, and overall constructability.
- Project cost estimates are further developed to match the approved budget.
Preparing for and building the project
In this phase, Metro can explain what happens after final design and before visible construction begins. The focus shifts from design development to implementation readiness.
What may happen in this phase
- Permit coordination and agency approvals
- Early utility work or advance preparation
- Construction planning and procurement steps
- Public information about what to expect before work begins
Launching RapidRide R Line service
This phase can celebrate the project opening and shift the page toward rider information. At that point, the focus becomes how to use the service and what customers need to know on day one.
What may happen in this phase
- Service launch information
- Station and rider amenities
- How to ride and service highlights
- Links to schedules, maps, and rider tools
FAQ
The future R Line spans approximately eight miles between Downtown Seattle and Rainier Beach along Rainier Avenue S. The transit corridor passes through a number of neighborhoods and offers connections to and from housing, employment, schools, public services, and transit. Not only is Rainier Avenue S a designated freight route that requires a wider lane so trucks can serve local businesses, it also has the highest number of crashes of any corridor in Seattle. Proposed R Line changes will not only improve reliability and transit travel time, but they will also create a safer place for all users of the area.
If property impacts are identified, the property owner will be contacted. If property owners are not contacted, it means there is no planned impact to the property. No matter the impact level, all property owners along the route will continue to receive project notifications throughout the project lifecycle.
Since 2020, the City of Seattle has completed several transportation improvements along the planned RapidRide R Line corridor, including new bus lanes on Rainier Avenue South—southbound between South Oregon Street and South Edmunds Street, northbound between South Alaska Street and South Walden Street, and northbound between South Walden Street and South State Street—new traffic signals at South Rose Street, South College Street, and South Grand Street, and new roadway crossings for people walking and rolling. Metro reviewed these changes and updated project plans to support faster and more reliable transit service. To learn more about the Rainier Avenue S. Bus Lane project,visit SDOT's website.
Metro's Care and Presence approach focuses on creating a cleaner, safer, and more welcoming transit system. Learn how Metro is improving cleanliness, increasing staff presence, supporting riders, setting clear expectations, and providing safety tips for riding the bus, using a wheelchair or mobility aid, and traveling by bicycle.
Sign up to receive updates
Resource library
Final Preferred Concept Engagement Summary (March to December 2020)
Explore the final preferred R Line concept, including proposed station locations, transit improvements and how community feedback influenced the project's final proposal before design work was paused in 2020.
Preferred Concept Engagement Summary (November 2019 to March 2020)
Learn how Metro gathered community feedback on the preferred R Line concept between November 2019 and March 2020. This summary highlights input on station locations, transit improvements and how community feedback helped shape the project's preferred concept.
Needs Assessment Engagement Summary (June to October 2019)
Learn how Metro engaged Rainier Valley communities during the first phase of the R Line project (June–October 2019). This summary highlights outreach activities, community feedback and the key themes that helped shape future design concepts.
Fact sheet (Summer 2026)
One-page document that summarizes the progress of the RapidRide R Line through Summer 2026, highlighting the benefits and what to expect next.
Also available in the following languages:
Corridor Planning and Upgrade Report Executive Summary (October 2020)
Get a high-level overview of the proposed RapidRide R Line, including planned corridor improvements, station locations, transit priority features, accessibility enhancements and estimated project costs.
Corridor Planning and Upgrade Report (October 2020)
Explore the complete technical report documenting the proposed RapidRide R Line, including corridor analysis, design recommendations, traffic modeling, station planning, accessibility improvements, cost estimates and supporting technical data.
Right-of-Way property informational letter (Summer 2026)
These letters were shared with property owners identified to have property potentially impacted by the RapidRide R Line along a half mile of the to-be RapidRide R Line.
RapidRide property owner brochure (December 2024)
Find out what property owners can expect during RapidRide planning, design and construction, including project access, property acquisition, compensation and construction impacts.