Road Resurfacing Projects
Paving work is underway through summer and fall 2026

King County resurfaces roads to improve pavement conditions, reduce potholes, and extend the life of the roadway. Roads are selected each year based on their condition and available funding.
Status update
October 14, 2026
On September 21, 2026, contractor crews working for King County Road Services began paving 3.23 miles of NE Big Rock Road between Duvall city limits and Kelly Road NE.
Work is scheduled Monday through Friday from 8 am to 5 pm. Flaggers will direct two-way traffic through a single open lane. Travelers should expect delays of up to 20 minutes.
Paving is a moving operation. This work is highly weather dependent and could be delayed or rescheduled.
Sign up for Road Alerts in your community to receive email or SMS text notifications about work in your area.
24/7 Road Helpline
Project overview
King County repairs and resurfaces roadways so roads last longer and are less expensive to maintain. Resurfacing also means fewer potholes and bumps for travelers.
Roads are selected for resurfacing each year based on their condition and on available funding.
Scheduled work dates are weather sensitive and subject to change.
What to expect in 2026
Crews anticipate using asphalt overlay to resurface roads in 2026. An overlay, also known as a top coat or resurfacing, is a process where a new layer of asphalt is applied over an existing paved surface. This technique is typically used when the existing pavement has minor damage like cracking, potholes, or mild deterioration, but the underlying base is still structurally sound.
Work will occur Monday to Friday generally between the hours of 8 am and 5 pm. Hours will be adjusted slightly as needed to avoid peak travel periods.
If at all possible, the contractor will place electronic message boards in the area at least 72 hours prior to the lane restrictions. Please check MyCommute for the latest information.
On most roads only the main travel lanes will be repaved. The center turn lanes and shoulders will not be repaved unless they are in poor condition. We will only repave the lanes that need to be repaired. Repaving the areas that are in the worst condition allows us to repave as many roads as possible without exceeding our yearly paving budget.
2026 Road resurfacing projects map
2026 Resurfacing locations
|
Roadway |
Extents |
Miles |
Location |
Type of paving |
Time of day |
Dates |
|
236 Ave SE to Loops west of SR 169 |
1.76 |
Enumclaw area |
overlay |
7 am - 5 pm |
Completed |
|
|
NE Cherry Valley Road |
450' East of house 28810 to house 30910 |
1.22 |
Near Duvall |
overlay |
daytime |
Rescheduled to 2027 |
|
Duvall City Limits to Kelly Road NE |
3.23 |
Near Duvall |
overlay |
daytime |
September 21 to October 30, 2026 (anticipated) | |
|
216th Ave NE |
from House 14503 to 214th Way NE |
0.38 |
Cottage Lake |
overlay |
daytime |
Rescheduled to 2027 |
| Avondale Road NE | Select sections from NE Woodinville Duvall Road to NE 155th Street | 2.6 | Cottage Lake | overlay | 9 am - 3 pm | Completed |
|
148th Ave NE |
147th PL NE to 140th PL NE |
0.43 |
Cottage Lake |
overlay |
daytime |
Rescheduled to 2027 |
|
Campbell Hill Elementary School to Renton Ave S |
0.5 |
Skyway |
overlay |
daytime |
summer 2026 |
|
|
Martin Luther King Jr Way S/SR 900 to S Langston Road |
0.21 |
Skyway |
overlay |
daytime |
Rescheduled to 2027 |
King County contractors also repair city (incorporated) roads
Smaller cities are invited to add roads to the contract with King County. For 2026, Normandy Park, Maple Valley, and Lake Forest Park have expressed interest. Questions about pavement repairs in these communities should be directed to the local cities.
Photos

Crews repaved a section of 190th Pl SE near Issaquah that needed repair. They started by grinding the pavement before laying down a fresh layer of asphalt.

Before and after paving on 140th Avenue SE in Fairwood. The photo on the right side shows temporary lane striping. Crews returned later in the year to apply permanent stripes on the road.