Eastgate Interceptor lining

King County rehabilitated a 2,400 foot-long section of twin sewer lines located in the Lake Hills Greenbelt Park in Bellevue.

Completed December 2018

Project description

King County has completed rehabilitating a 2,400 foot-long section of the twin Eastgate Interceptor lines. This project will extent the useful life of this pipeline another 50 years. This project was located in the Lake Hills Greenbelt Park Bellevue (see map below), and included:

  • Construction of access roads within the park to reach the project work areas
  • Dewatering operations where sewage flows were directed around the work area so the pipe could be dried and then cleaned for the lining operations
  • Repair of corroded sections of the pipeline using a trenchless, below-ground construction lining method called ‘cured in place pipe’ (CIPP).

Schedule

Work on this project began in April 2018 and the project was substantially completed in December 2018.

There was extensive natural restoration done for this project. Restoration will be monitored until at least 2023.

Project area

project area map

Download map and map with aerial background.