Road Resurfacing Projects
2026 paving season complete. Additional improvements are planned for 2027.

King County resurfaces roads to improve pavement conditions, reduce potholes, and extend the life of the roadway. Roads are selected each year based on their condition and available funding.
Status update
November 20, 2026
On November 9, 2026, contractor crews working for King County Road Services completed paving 3.23 miles of NE Big Rock Road between Duvall city limits and Kelly Road NE. This work marks the completion of this year's resurfacing efforts and the transition to the 2027 program.
2027 resurfacing locations and schedules will be posted below once they are selected. Any locations not completed during the 2026 construction season will be incorporated into the 2027 program. We will continue to update this website and MyCommute as additional information becomes available.
Sign up for Road Alerts in your community to receive email or SMS text notifications about work in your area.
24/7 Road Helpline
Project overview
King County repairs and resurfaces roadways so roads last longer and are less expensive to maintain. Resurfacing also means fewer potholes and bumps for travelers.
Roads are selected for resurfacing each year based on their condition and on available funding.
Scheduled work dates are weather sensitive and subject to change.
2026 Road resurfacing projects map
2026 Resurfacing locations
|
Roadway |
Extents |
Miles |
Location |
Type of paving |
Time of day |
Dates |
|
SE 400th Street |
236 Ave SE to Loops west of SR 169 |
1.76 |
Enumclaw area |
overlay |
7 am - 5 pm |
Completed |
|
NE Cherry Valley Road |
450' East of house 28810 to house 30910 |
1.22 |
Near Duvall |
overlay |
daytime |
Rescheduled to 2027 |
|
Duvall City Limits to Kelly Road NE |
3.23 |
Near Duvall |
overlay |
daytime |
Completed | |
|
216th Ave NE |
from House 14503 to 214th Way NE |
0.38 |
Cottage Lake |
overlay |
daytime |
Rescheduled to 2027 |
| Avondale Road NE | Select sections from NE Woodinville Duvall Road to NE 155th Street | 2.6 | Cottage Lake | overlay | 9 am - 3 pm | Completed |
|
148th Ave NE |
147th PL NE to 140th PL NE |
0.43 |
Cottage Lake |
overlay |
daytime |
Rescheduled to 2027 |
|
Campbell Hill Elementary School to Renton Ave S |
0.5 |
Skyway |
overlay |
daytime |
Completed | |
|
Martin Luther King Jr Way S/SR 900 to S Langston Road |
0.21 |
Skyway |
overlay |
daytime |
Rescheduled to 2027 |
King County contractors also repair city (incorporated) roads
Smaller cities are invited to add roads to the contract with King County. For 2026, Normandy Park, Maple Valley, and Lake Forest Park have expressed interest. Questions about pavement repairs in these communities should be directed to the local cities.
Photos

Crews repaved a section of 190th Pl SE near Issaquah that needed repair. They started by grinding the pavement before laying down a fresh layer of asphalt.

Before and after paving on 140th Avenue SE in Fairwood. The photo on the right side shows temporary lane striping. Crews returned later in the year to apply permanent stripes on the road.