Eastside Interceptor Section 14 Joint and Culvert Rehabilitation
King County will repair a culvert that runs under the Eastside Interceptor Section 14 (ESI 14) sewer pipe. Crews will also build a retaining wall to support the slope at the culvert site and stabilize the stream nearby. This work will help protect the pipe from potential damage in the future. The repair project will require closing the Cross Kirkland Corridor (CKC) between Northeast 52nd Street and 108th Avenue Northeast.
ESI 14 sewer pipe is a 7-foot diameter pipe owned by King County. The pipe carries about 2.6 million gallons of wastewater a day during dry weather to the County’s South Treatment Plant in Renton. In July 2025, King County and City of Kirkland crews found a leak from the County’s ESI 14 sewer pipe that was entering the culvert. King County coordinated with Public Health – Seattle & King County, and no public health risk was identified.
Crews completed repairs to the ESI 14 sewer pipe in February. They installed a 3,000-foot temporary above-ground diversion pipe to maintain sewer service. This pipe will remain on the west side of the trail to support summer culvert repairs. After the work is completed, crews will remove the diversion pipe and restore the site.
The Eastside Interceptor is one of the largest conveyance pipes in our regional sewer system. It collects and carries untreated wastewater from local municipal sewer systems between Kirkland and Renton and sends it to South Treatment Plant, where it is cleaned and released into Puget Sound.
Project update
August 4, 2026
ESI-14 Culvert Construction Work Starting Soon
King County will repair a culvert that runs under the Eastside Interceptor Section 14 (ESI 14) sewer pipe. Crews will also build a retaining wall to support the slope at the culvert site and stabilize the stream nearby. This work will help protect the pipe from potential damage in the future. The repair project will require closing the Cross Kirkland Corridor (CKC) between Northeast 52nd Street and 108th Avenue Northeast.
Initial work on the Trail to prepare the work site will start in August.
Preparation work will include:
- Occasional trail closure.
- Connecting above-ground diversion pipe to maintain service.
- Using heavy construction equipment on CKC trail.
- Trail detour established.
For more details, read our latest project email.
Past project updates
- Comment on ESI-14 Joint Repairs and Culvert Rehabilitation Project environmental review by August 3!, July 17, 2026
- Cross Kirkland Corridor Trail closed near Northeast 52nd St. on Tuesday, March 24, March 18, 2026
- Pipe repair complete, Cross Kirkland Corridor trail opening soon, February 13, 2026
- Wastewater to be diverted to temporary above-ground pipe in Kirkland, January 13, 2026
- Cross Kirkland Corridor Trail to close as early as Monday, January 5, December 29, 2026
- Cross Kirkland Corridor Trail to temporarily open as early as December 11, December 11, 2025
- Eastside Interceptor Section 14 joint rehabilitation underway, October 15, 2025