Skip to main content

Road Resurfacing Projects

Work scheduled for 2024

Paving in unincorporated King County.

Status update

In 2024, paving work will occur both during the daytime and nighttime. Residents in the area can expect noise while crews resurface portions of the road.

The work is scheduled to occur between July and October 2024. Specific dates will be posted on this website and on MyCommute. Sign up for Road Alerts in your community to receive email or SMS text notifications about work in your area.

Paving work is weather dependent, and dates are subject to change.

For the most up-to-date status, please check MyCommute.

24/7 Road Helpline

24/7 Road Helpline

Call us for help at 206-477-8100 or 1-800-527-6237 with road maintenance and traffic safety issues in unincorporated King County — 24 hours a day

Project overview

King County repairs and resurfaces roadways so roads last longer and are less expensive to maintain. The resurfacing also means fewer potholes and bumps for travelers.

Roads are selected for resurfacing each year based on their condition and on available funding.

Scheduled work dates are weather sensitive and subject to change.

2024 Road resurfacing projects map

2024 Resurfacing locations

ROAD TYPE OF WORK/EXTENT MILES DATES TIME
SE 60th Street Between 18000 block & 189th Avenue SE; 189th Avenue SE between SE 60th Street & Issaquah City limits 0.75 Completed in August 2024 8 a.m. to 4 p.m.
N 145th Street Westbound lanes on N 145th St between Evanston Ave N and Linden Ave N  982 feet Completed in October 2024 8 a.m. to 5 p.m. daily
NE 132nd Street
Between Avondale Road NE and Bear Creek Road/133rd Street 0.32

Completed in October 2024 Signal work: 8 a.m. to 4 p.m. daily 
NE Novelty Hill Road Sections between 187th Court NE and 203rd Avenue NE 0.41 Completed in September 2024  Night paving: 7 p.m. to 4:30 a.m.
164th Avenue SE From SR-900 to SE 128th Street. 0.84 Completed in October 2024 Night paving: 7 p.m. to 4:30 a.m. 
SE North Bend Way  Snoqualmie Casino Roundabout to 384th Avenue SE  0.65 Completed in September 2024  Night paving: 7:00 p.m. to 4:30 a.m.
SE North Bend Way  North Bend city limits to 384th Avenue SE  0.65 Completed in July 2024 Daytime paving: 7 a.m. to 5 p.m. 
NE Cherry Valley Road  270th Place NE to 400' East of 28810 1.60 Completed in August 2024 Daytime paving: 8 a.m. to 5 p.m.
SE 400th Street  188th Avenue SE to 236th Avenue SE 3.03 Fall 2024 Daytime paving: 7:00 a.m. to 5:00 p.m.
356th Drive SE SR 202 to 362nd Avenue SE 1.62 Prep for paving completed in July 2024; paving summer 2025
Daytime weekday paving
Wilderness Rim Loop 430th Avenue SE clockwise around to Cedar Falls Way 1.49 Prep for paving spring 2025; paving summer 2025
Daytime weekday paving
280th Avenue SE SE High Point Way to end of the county-maintained road 0.63 Spring 2025
Daytime weekday paving
NE Tolt River Road City limits of Carnation to 361st Avenue NE 2.95 Prep for paving spring 2025; paving summer 2025
Daytime weekday paving
SE Mirrormont Blvd/245th Avenue SE Issaquah Hobart Rd SE to SE Tiger Mountain Rd 2.11 Paving in summer 2025 Daytime weekday paving
Mountain View Road NE
318th Avenue NE to NE 190th St 1.15 Completed in July 2024
Daytime weekday paving
318th Avenue NE Mountain View Rd NE to NE 183rd St 0.16 Completed in July 2024
Daytime weekday paving
Avondale Rd NE Near 16205 300’ by 25’ patch Spring/Summer 2025
Daytime weekday paving
Avondale Rd NE NE 159th St 900’ by 30’-40’ patch Spring/Summer 2025 Daytime weekday paving
Avondale Rd NE Avondale Pl NE to Avondale Pl NE 2000’ by 11’ patch Spring/Summer 2025 Daytime weekday paving
190th Place SE
Between Issaquah city limits and SE 60th St 2,230 feet Completed in August 2024 Full closure. Emergency vehicle access only. 

What to expect in 2024

Work will occur Monday – Friday generally between the hours of 8:30 a.m. and 4:30 p.m. Hours will be adjusted slightly as needed to avoid peak travel periods. On some roadways, work will be completed between the hours of 7:00 p.m. and 4:30 a.m., Monday night through Saturday morning.

For all roadways, the contractor will place electronic message boards in the area at least 72 hours prior to the lane restrictions. Please check MyCommute for the latest information.

On most roads only the main travel lanes will be repaved. The center turn lanes and shoulders will not be repaved unless they are in poor condition. We will only repave the lanes that need to be repaired. Repaving the areas that are in the worst condition allows us to repave as many roads as possible without exceeding our yearly paving budget.

King County contractors also repair city (incorporated) roads

Smaller cities are invited to add roads to the contract with King County. In 2024, Beaux Arts Village, Black Diamond, Normandy Park, and Maple Valley have expressed interest. Questions about pavement repairs in these local cities/communities should be directed to the local cities. 

Photos

Crews repaved a section of 190th Pl SE near Issaquah that needed repair. They started by grinding the pavement before laying down a fresh layer of asphalt. 

 

Before and after paving photo.

Before and after paving on 140th Avenue SE in Fairwood. The photo on the right side shows temporary lane striping. Crews returned later in the year to apply permanent stripes on the road.

expand_less