Carey Creek Fish Passage Project at 276th Ave SE

Project to restore fish passage in Carey Creek, a tributary to Issaquah Creek near Hobart, Washington.

Concrete structure in Carey Creek that is a partial barrier to fish passage.
Carey Creek fish passage barrier at 276th Ave SE

Project overview

This project will:

  • Remove and replace the crossing at 276th Ave SE with a fully fish passable structure.
  • Restore access to over 3 miles of high-quality fish habitat upstream of this project. Species affected include Chinook, coho, steelhead, and other aquatic species.
  • Increase the ability for wildlife to safely cross under the roadway through the new, larger opening.
  • Not increase current levels of flood and erosion risk to people, property and infrastructure.
Map showing the location of the Carey Creek Fish Passage Project at 276th Ave SE upstream of State Route 18 and the confluence with Holder Creek and Issaquah Creek.
Carey Creek at 276th Ave SE Fish Passage Project location map

The challenge

  • A fishway was installed downstream of the existing culvert several decades ago to help fish make it upstream of 276th Ave SE. The fishway is now currently acting as a partial barrier to migratory fish like our local salmon species.
  • The current crossing is a double culvert with baffles and a large concrete apron on the downstream end of the crossing.
  • Over time, this structure has eroded a large scour pool at the downstream end of the fishway. This pool has left the entire crossing structure perched over the downstream creek.
  • The culvert will be replaced with a new bridge crossing that will meet modern road, structural, and fish passage standards.

Project timeline

Preliminary Design – Complete
Final Design & Funding Target – 2026-2027
Construction Target – Summer, 2028 (contingent on construction funding)

Existing funders

  • Brian Abbot Fish Barrier Removal Board
  • King County Cooperative Watershed Management Grant (King County Flood Control District).
  • King County Surface Water Management Fees

Project documents

For reports, engineering documents, or other additional project information, please contact the project manager, Alex Hallenius, at alex.hallenius@kingcounty.gov.