Skip to main content

NE Tolt Hill Road Slide Repair Project

Project completed in summer 2024

The temporary traffic signal on NE Tolt Hill Road was removed on September 18, 2024. Crews completed the replacement of the new retaining wall under the west approach of the bridge. 

Overview

Road Services replaced the previous damaged retaining wall with a new deep retaining wall that is designed to prevent erosion and provides better protection for flood events. This project improves safety for travelers and restores the stability of soil under the west approach to the Tolt Bridge, over the Snoqualmie River near Carnation, WA.

King County removed the existing 55-foot-long gabion retaining wall and replaced it with an updated 80-foot-long soldier pile retaining wall. This shores up the soil under the southwest bridge approach and improve the stability of the nearby slope. This bridge is an important part of the east/west corridor in the Snoqualmie River Valley and a critical part of the flood evacuation route. The shoulder that was closed in March 2023 has reopened.

24/7 Road Helpline

24/7 Road Helpline

Call us for help at 206-477-8100 or 1-800-527-6237 with road maintenance and traffic safety issues in unincorporated King County — 24 hours a day

Project location

 

The active construction zone took place west of and under the bridge. Construction equipment was stored on one of the two lanes of the bridge. The Tolt Bridge is located over the Snoqualmie River to the west of Carnation, WA.  View larger image (661KB)

Timeline 

  • Design Complete: June 2023 
  • Construction Contract Advertised: December 2023 
  • Construction Bids Opened: January 2024 
  • Construction Work: May to September 2024

Budget and funding  

Total cost: $2.63 million. This project was funded by FHWA Emergency Relief.  

Frequently asked questions

The Tolt Bridge itself is not in need of replacement. The bridge is inspected regularly per federal requirements. Any issues or repairs needed for the bridge are identified and repaired to keep it serviceable and safe for the public.  

In February 2020, following a significant rainstorm, settlement and movement of the gabion wall was discovered, and engineers implemented survey and visual monitoring of the ground movements from that time. In addition, a real-time monitoring system was installed on the tilted wall and the west approach to the bridge to allow the engineers from their office to monitor the movement of the impacted area. 
In February 2020, after an atmospheric river caused intense rain and major flooding, the Snoqualmie River crested (the highest level a river reaches before it goes back down) at an elevated level. The high flow of the Snoqualmie River and the saturation of the soil caused settlement and tilting of the gabion walls and thus failed to retain the soil under the bridge approaches.
After the February 2020 storm, the existing retaining wall settled and tilted outwards making it less effective. The retaining wall, bridge supports, and the Tolt Bridge is routinely monitored for changes and areas of concern. Road Services is replacing the existing and damaged shallow retaining wall with a deep and longer retaining wall structure. It is designed to prevent erosion and lateral soil movement and will provide better protection for flood events. 
Retaining walls are structures that are designed and constructed to hold soil in an embankment.  

Gabion retaining walls are shallow walls built of rectangular wire mesh boxes filled with rock or other materials, then stacked in “cells.” They are most commonly used as retaining wall structures and can often be seen along the sides of roads and highways holding back cliffsides to retain soil.

Soldier Pile retaining walls are designed by geotechnical/structural engineers to prevent soil settlement, lateral movement, and erosion that can undermine an existing structure. During construction crews placed large steel piles in pre-drilled holes deep in the ground and then place panels between the piles.

Sample photo:  gabion retaining walls are made of wire mesh boxes and filled with rocks.

 

Deep soldier pile retaining walls are built to prevent the lateral movement of soil.

 

 

Project photos

August 2024 – The final layer of lightweight concrete was poured to reinforce the area between the bridge and the steel soldier piles.

 

Geoscience consultant testing concrete.

August 2024 – A geoscience consultant guides a steel rod through a drilled hole in the pavement on NE Tolt Hill Rd to ensure that the lightweight concrete filled the area beneath the pavement of the bridge.

 

Crew member directs the lighweight concrete pour.

August 2024 – A crewmember directs the first layer of lightweight concrete pour to fill and reinforce the space beneath the bridge. Lightweight concrete is made with lighter materials than traditional concrete.

 

Angled iron segments installed.

August 2024 – Angled iron segments were installed to support timber laggings. Timber laggings are wood planks placed between the steel soldier piles to protect against impact, abrasion, and corrosion.

 

Crew members place timber beams in between soldier piles.

July 2024 – Crews place timber beams in between the soldier piles, which will retain the lightweight concrete that will be poured between the roadway and the piles.  

 

Workers weld studs into soldier piles.

July 2024 – Metal studs are welded into the soldier piles, helping it to resist force and movement. These studs will also serve as an anchor to rebars that will be installed to support the outer wall.  

 

Newly placed soldier piles will provide deep structural support and improve stability of the nearby slope.

July 2024 – The newly placed soldier piles will provide deep structural support and improve stability of the nearby slope. 

 

A large drill, called an auger, drills into the soil below the bridge on NE Tolt Hill Rd to prepare for the new steel soldier piles.

July 2024 – A large drill, called an auger, drills into the soil below the bridge on NE Tolt Hill Rd to prepare for the new steel soldier piles. 

 

Tolt Bridge with temporary single lane closures in place.

May 2024 – The bridge is open to all traffic but requires temporary single lane closures at the west approach of the bridge. 24 hours a day, 7 days a week a portable traffic light is alternating two-way traffic into the one open lane.

 

November 2023 – Orange traffic cones were in place to block vehicles from using the shoulder of the bridge directly above the existing wall. 

 

King County Road Services will replace a damaged retaining wall supporting NE Tolt Hill Road west of Carnation, WA.

November 2023 – Construction will require temporary single lane closures and will alternate two-way traffic into the one open lane using a portable traffic light. Once construction has concluded, the current shoulder restriction will be removed. 

expand_less