Fall City on-site community septic system
Construction update
A worker sits on a machine that drills holes on the shoulder of SR-202 for the future septic system connection in Fall City. (Photo taken in October)
November 4, 2024
Contractor crews move into the next phase of work on the project in November. They will drill on the north/south streets in the alley behind local businesses. If your local business takes deliveries from the back alley, this may affect the delivery process. The contractor will minimize closures in the alley to reduce the impact on local business.
All parking in front of local businesses on SR-202 has been restored.
Questions or concerns?
Send email to asklocalservices@kingcounty.gov
Overview
Fall City is an unincorporated rural town with a population of less than 5,000 people and more than 40 businesses in the business district. The town sits where the Snoqualmie River and Raging River come together. The area is important to local Native American tribes.
This project supports the Fall City Business District and the community’s economic future.
The Fall City Business District has many businesses and residences with broken wastewater systems. A 2016 survey showed that only 14 of 62 properties in the business district had updated septic systems. The failing older systems posed a public health risk to the surrounding community and an environmental threat to nearby rivers.
Currently, local businesses cannot expand or keep up with changing demands from customers. For more than 10 years, the Fall City community asked for help to solve this problem.
With the support of state and local elected leaders and King County, we are moving forward with the Fall City on-site septic project, which will connect 46 businesses to an underground pre-treatment facility. The project will repair all failing and non-conforming systems and the new system will provide capacity for conservative growth in the business district. It will treat waste to the highest quality standards required by the Washington State Department of Health.
Location
The project site is in the Fall City Business District, next to the Snoqualmie River and near the intersection of state routes 202 and 203.
What to expect during construction
- Access to local business will be maintained throughout construction.
- Crews will work during the day. Work will sometimes be noisy.
Temporary closures and parking impacts
- Bernard Memorial Park, near the Roadhouse Inn, will be completely closed to the public for up to 12 months.
- The alley behind businesses on Redmond-Fall City Road SE between 334th Place and Preston-Fall City Road SE will be closed intermittently in 2025 and early 2026.
- Parking on the south side of Redmond-Fall City Road SE will be intermittently unavailable during active construction in 2025 and 2026.
How to stay informed
- Project updates will be posted on this page
- Contact the Fall City Community Association (visit the website or send email)
- Check with King County Local Services during our office hours at the Fall City Library on first and third Tuesdays
- Road closure dates and times will be posted on MyCommute
Project schedule
-
August – October 2024
Build drain field
-
October – December 2024
Install main sewer line
-
January – September 2025
Install and commission treatment facility
-
July 2025 – March 2026
Install and connect septic tanks
-
April 2026
Project complete