Gunter Levee Project
This webpage includes an overview of the project and anticipated schedule. As the project is developed opportunities for public input will be included.
Project overview
The Gunter Levee is located in the City of Tukwila along the west left bank of the Green River when looking downstream and reduces flood risks to commercial areas of Tukwila.
The Gunter Levee project will evaluate current conditions between river miles 15.9 and 16.8 and design a plan to reconstruct and improve the flood facility. Recent studies found that the riverbank in this area is too steep and could be at risk of failing in the future. The new flood facility will be taller to contain larger floods and wider to allow for a gentler slope. The project plan will also consider other ways to improve habitat and recreational opportunities in the area.
King County, as the primary service provider to the King County Flood Control District, is currently working on planning and technical studies, and final design of the new flood facility is anticipated in 2023, pending right of way negotiations. Construction is expected to start in 2027.
Reconstruction of the levee is important for reducing the potential of catastrophic flood emergencies and earning levee recertification from FEMA, which can influence future development opportunities in this commercial setting.
What is a levee?
A levee is a raised structure built along a riverbank to contain, control, or divert the flow of water and protect the land along the river from temporary flooding. A levee is usually made of earth and runs parallel to the course of a river. Levees can occur naturally when rivers deposit sediments along the bank following times of high river flows or they can be constructed by people.
The original levees along the Green were likely a combination of both. Many of the levees along the Green were first constructed when farmers removed sediments from the river and piled them along the banks to help prevent flooding of their farmland. Over time rock was added to keep the levees in place and more material was added to the top of the levee.
The levees along the Lower Green River were not originally intended to protect homes and businesses and often require repairs and improvements to reduce the risks of flooding.
Project goals
- Evaluate existing levee conditions between river miles 15.9 and 16.8.
- Design and construct a new flood facility that meets current engineering standards to reduce risk and impacts of catastrophic flooding.
- Identify how the project can improve fish and wildlife habitat and provide opportunities for recreation.
Project schedule
Activity | Date |
---|---|
Planning and alternatives selection | 2020 to Spring 2024 |
Preliminary design (30 percent) | Spring to Fall 2024 |
Final design and permits | Fall 2024-Fall 2026 |
Construction | 2027 |
Construction impacts
King County is working to limit the impacts of construction. Construction may temporarily impact use of roads, sidewalks, trails, and parks in the area.
We will update this webpage with impacts to roads, sidewalks, trails, or parks in the area as the project moves through design and permitting. We will also post signs and flyers near the project site and notify local businesses and residents before and during construction. To receive updates, please sign up for the project email list.